K. Barnett & Sons to Begin Road Work

K. Barnett & Sons to Begin Road Work

K. Barnett and Sons is planning on beginning work on Fred Daugherty Ave, Peacock Pl, and Thornton Ave, next Monday, July 6, 2020. The work consists of the pulverization of the existing asphalt surfacing, grading, and placement of new hot-mix asphalt. We anticipate the work to be complete, weather permitting, by the third week of July.

The work will be performed Monday through Friday between the hours of 7:00 am and 5:00 pm. During this time there will be no on-street parking, and the work area will be closed to all but local traffic. The work area will be open if no work is taking place, but on street parking will be limited by the presence of our equipment. Please have vehicles out of the work zone by 7:00 am.

If you have any questions or specific concerns please don’t hesitate to contact K. Barnett and Sons at (575) 762-4407.