Norris Street Project

July 11, 2013

NORRIS STREET ROADWAY IMPROVEMENT PROJECT

On February 21, 2013, the Clovis City Commission awarded the project to K. Barnett & Sons, Inc., for $3,966,809.98.  The proposed project will include roadway improvements, bike lanes, sidewalks, and storm drain.  The first phase of the project is currently underway from Mollie Circle to Wilthite Road and also includes the construction of a drainage ditch from Norris St. to a playa lake located to the east.  The first phase is scheduled to last until August.  The second phase of the project will be from Mollie Circle to Llano Estacado Blvd. and is scheduled from August to February 2014.  During construction please adhere to all construction signs and seek an alternate route when possible.  Should you have any questions please contact Justin Howalt, City Engineer, at jhowalt@cityofclovis.org.

 

July 18, 2013

WEATHER EVENTS CAUSE DELAY IN NORRIS STREET PROJECT

Due to the inclement weather in June and July the schedule for opening Norris Street from Wilhite Road to Mollie Circle has been delayed.  The roadway was originally scheduled to open prior to the start of the school year but has now been rescheduled to open in late August pending further delays.  Accommodations will be made to provide access to all Mesa Elementary parking lots as well as pedestrians.  All vehicular traffic will need to enter the school from Norris Street via Wilhite Road.  The normal parent drop off patterns will remain in effect.

Should you have any questions regarding the construction please contact City Engineer, Justin Howalt at 769-2376.

 

final typical section (1)